The Building of Westminster
At the beginning of the 19th century in
England, the building industry was undergoing major changes. For many years,
even centuries before, building had been done by independent craftsmen belonging
to guilds, or Companies, who usually worked directly for a client. The end of
the 1700s, however, was the time of transition from these old, established ways
to what eventually became known as the ‘modern system’ of contract labour and
measuring to determine costs.
There were two key characteristics of this new
procurement system. First was the use of detailed drawings and design,
completed before the work began. The second was the preparation of cost
estimates for the project, on the basis of the design drawings. The two
significant outcomes of these characteristics, that became the foundations of
the modern system, were the shift to competitive tendering and the emergence of
the professions of architects, engineers, surveyors and contractors during the
rebuilding of London after the Great Fire of 1666.
In the 1800s the general contractor emerged as a new
type of firm, winning projects through competition, responsible for organising
the building process, and employing craftsmen to undertake work directly or as
subcontractors. By the middle of the 19th century large contracting
businesses had taken on the form that in many ways we still see today, and
procurement and contracting was using a recognizably similar system.
The construction of Westminster from 1837 was one of the
first major buildings to be done using the ‘modern system’ of procurement and contracting,
with detailed drawings from the architect and a bill of quantities (BQ) with
full estimates based on them. Under the earlier system of measure and value,
costs had been determined on completion by a measurer, originally a tradesman, and
over time this became a specialised task done by surveyors.
The story of the building of the New Palace of
Westminster (the British Houses of Parliament) in the mid-nineteenth century is
instructive. As told by Kingsford in Builders
and Building Workers, the project used new engineering techniques and
machinery, the skills of hundreds of traditional craftsmen and a huge work
force managed by some of the largest contractors. There were between 400 and
1,400 men employed on the project at any one time in 1848, 776 were on site,
120 in quarries and 335 in the contractor’s workshop. The project was expected
to take six years and cost £700,000, but actually took almost 30 years and cost
over £2 million (well over £500 million or $1 billion in today’s money).
There were disputes between the architect who won the
design competition, Charles Barry, and pretty much everyone else involved,
starting before construction began. There were arguments over the initial
design, over the estimates and the architect’s fees, there were disputes over
contract prices and supply problems with the materials. The designer of the
heating and ventilation system fell out with Barry and the two became enemies. The
masons went on strike for 30 weeks after a foreman swore at them.
The project was carried out through a series of
successive contracts awarded through competitive tender or by recommendation by
Barry. The first two contracts were let by the government department in charge.
The third contract was put out for tender to eight firms recommended by Barry,
and was won by one of the largest London contractors (Grissell and Peto) who
were then given the following four contracts by negotiation without further
competition.
In the third contract the prices were set by the builder
and agreed to by the architect, however in the fourth contract prices were
determined by the government department and set lower than prices arrived at
through competition. The assumption was that the new industrial technology
appearing on building sites, such as mechanical scaffolding and steam powered hoists
and pumps, would reduce the costs. These contracts had detailed specifications
on all aspects of the work and were priced in a form recognizably similar to a
modern bill of quantities. The work of each trade was specified separately. The
contractor later renegotiated a new set of prices as these were profitless contracts
otherwise.
The 1844 contract for ‘finishings’ was on a unit price
basis, reduced by 22 percent by the Office of Works and Public Buildings on the
basis that the new machinery coming into use would save time and labour. As it
turned out much of the carpentry work, although initially carved by new machines,
had to be completed by hand at significant extra cost. Grissell terminated the
contract in 1845 and the complex negotiations that followed went on over many
years. Building agreements in those days did not include provision for claims and
variations.
This was also a time a rapid technological innovation
and development, both by and for contractors. Satoh has six chapters on 19th
century technical advances in his Building
in Britain, covering stone, wood, bricks, components, pumps and lifting
machinery. Like other industries the widespread availability of steam power was
transformational in the application of new machinery and the use of
mechanization on building sites slowly increased. There was also an ongoing
transfer of site work into the contractors' workshops. For the
largest firms these were huge, William Cubitt (contractor brother of property
developer Thomas Cubitt) had 25 acres on the Isle of Dogs in 1845, complete
with wharves, sawmills, cement kilns, an iron foundry, brickfields, a pottery
and so on, linked by an internal railway and employing about 800 men.
Westminster was also where many of these new technologies and innovations were
used, some of them for the first time.
During the 19th century general contractors,
often winning projects in competitive tenders, became responsible for
organising projects and employing workers. While there were recognizable
elements of the old system still in use in the 19th century, the
building industry was becoming a complex and confusing conglomeration of
businesses and individuals. Many of these characteristics of the industry, as
the example of the building of Westminster shows, are still part of the
building and construction industry today. The same can be said for issues in
procurement and contracting.
Many major modern projects have the same or similar
story arc, such as the Scottish Parliament building (initially budgeted for £40
million and three years construction but taking six years and costing over £400
million.) and Australia’s Parliament House. The Sydney Opera House is famous
not only for its location and design but also for its probable world record
cost blowout of 1,400%. Other famous cost overruns in recent years include the
Boston Big Dig and Denver airport, and all these projects had problems
recognizably similar to those found in the building of the Palace of
Westminster.
Satoh closes his book with a series of quotes from opponents
of the modern system from the mid-nineteenth century. These include: poor
quality work due to low price bidding, or subcontracting; builders undercutting
each other to win work under the new system of competitive tenders; the lack of
provision for variations in fixed price contracts; unjustified claims by
contractors; arbitrary decisions by superintendents and architects; non-payment
by clients; and collusion between contractors. To address these issues the procurement
and contracting system began to incorporate increasingly detailed drawings and
specifications, and a schedule of prices was often attached for claims and
variations. The unilateral nature of the contract led to the drafting of the
Conditions of Contract.
In 1870 the terms of a document called the Heads of Conditions of Builders Contracts
was agreed between the Royal Institute of British Architects and the Builders’
Society This established the basic outline and principles of the standard
building contract which could then be varied to particular circumstances, and
addressed the concern of builders who felt that previous contracts made no
provision for variations in materials prices or the cost of extra work. Bills
of quantities were introduced as part of the contract in 1902, after many
revisions in the meantime, and this remained the basic form until 1931 when the
Joint Contract Tribunal was set up and the standard forms of contract came into
use. These are still the basis of the majority of building contracts in the UK
today.
In procurement and contracting in the building
and construction industry change happens slowly. This may, however, not be true of the 21st century.
This is one in a series of procurement case studies. Other ones are on the building of the the Scottish parliament house Holyrood Building in 1997 and Heathrow Terminal 5.
References
Kingsford, P.W. 1973. Builders and Building Workers, London: Edward Arnold.
Satoh, A. 1995. Building
in Britain: The Origins of a Modern Industry, London: Scholar Press.