The Holyrood
Building
The story of
the building of the new Scottish parliament house, The Holyrood Building, is
another instructive case study. In 1997 it was announced that the new
parliament building was to be constructed and the cost estimate was £40
million. A design competition was held, one year later in 1998, and a
construction management contract was awarded to Bovis Lend Lease at the
beginning of 1999.
The initial client was the Scottish Office, then after work started this was transferred to the Parliamentary Corporate Body, and later the Presiding Officer and an architectural advisor were added. A report in 2000 identified poor communication between the client and contractors as increasingly costly.
The initial client was the Scottish Office, then after work started this was transferred to the Parliamentary Corporate Body, and later the Presiding Officer and an architectural advisor were added. A report in 2000 identified poor communication between the client and contractors as increasingly costly.
Contracts were
based on concepts, not on a detailed finished design. The concept design also
changed during construction, with floor space first increasing from 11,000 m²
to 18,000 m² and ending up at 33,000 m². There were also increased anti-terror
security measures including toughened glazing, which added another 10% to the final
cost.
This all led
to very many variations, in a six-month period between October 2002 and May
2003 there were 1,825 architect instructions which led to 4,600 instructions to
trade contractors, with nearly 5000 variations in six months. Despite a design
freeze that began in April, in May 2003 there were another 545 architect’s
instructions. The time and cost implications are obvious. A report by the
Auditor General in 2004 concluded that over 2000 design changes to the project
were a major factor in the cost overrun.
During
construction the lead architect died and the project director resigned. There
were conflicts between the two architectural practices involved, and between
them and the contractors. The Fraser Inquiry was critical of their
dysfunctional relationship, poor communication and their claim, “without basis”
that the building could be completed for £50 million.
By June 2001
the costs had escalated to £230 million. In 2002 the cladding contractor went
into liquidation and the price increased to £300 million. By the time the
building opened in September 2004 it was three years late and had cost a great
deal more than the initial estimates. The eventual cost reported in 2007 was
£414 million, 10 times the original estimate.
An inquiry was set up and the report was published in 2004. A major focus
of the Fraser Inquiry was whether the procurement method or the client had
caused the problems. A construction management contract is typically used on
integrated design and construction projects, which is its strength, but is not
particularly good at managing budgets. The original budget was obviously much
too low, and this led to a lot of unwanted and probably unnecessary publicity
about cost overruns. The main findings of the inquiry were the unrealistic
nature of the initial cost estimates, use of a procurement model that passed
risk wholly onto the state client, conduct of the tendering process and
choosing the contractor, and security concerns that added to the cost but could
have been anticipated. The conduct of civil servants was questioned.
The Fraser Inquiry identified two fundamentally flawed decisions. The
first was procurement using a construction management contract instead of a
Private Finance Initiative contract. Second was the insistence on a rigid
program. The Scottish Office decided to use a construction management contract
to speed construction, but without evaluating the financial risks of doing so,
and without asking Ministers to approve it. Officials decided that
rapid delivery of the new building was to be the priority, but that quality
should be maintained, so cost blowouts were inevitable.
The client was obsessed with early completion and failed to understand
the impact on cost and the completion date if high-quality work and a complex
building were required. In attempting to achieve early completion, the
management contractor produced optimistic programs, to which the architects
were unwise to commit. The main causes of the slippage were delays in designing
a challenging project that was to be delivered against a tight timetable.
Perhaps most damning in the inquiry’s report was the finding that senior
civil servants withheld information on the problems between contractors and
architects and the rising cost of the project from ministers. Ministers were
not informed of concerns within the Scottish Office over the cost of the
project and officials did not take the advice of the cost consultants, a
serious failure of accountability.
In the final
indignity the completed project suffered from flooding, as the original site
had been a brewery and there were hidden underground springs. Then in 2006 one of
the beams in the debating chamber swung loose due to missing and damaged bolts
and poor glue, and the MPs were evacuated.
The lesson
that is usually drawn from the Scottish Parliament building is that the client
did not know what they wanted and proceeded with a brief that was poorly
developed. However, the conduct of the civil servants involved was, in my view,
deplorable. After the Fraser Inquiry’s report was handed down there were
further investigations by the Scottish Parliament into their conduct, however
no action was taken against any of the individuals involved.
Clearly, when
civil servants get involved in these large complex projects, guidelines
on governance need to be established and rigorous standards need to be
enforced. One of the recommendations of the report was that independent
advisers should be employed and those advisers need to have direct access to
ministers, without their advice being filtered by public officials.
Holyrood is an
extensively documented project. The link to the Fraser Inquiry report is below,
the Conclusions and Findings are the most relevant. There is a Wikipedia page
that is comprehensive, including a timeline of cost increases and many links.
This is one in a series of procurement case studies. Other ones are on the building of the British parliament house at Westminister in 1837 and Heathrow Terminal 5.
No comments:
Post a Comment
Thank you for your comment and for reading the blog. I hope you find it interesting and useful. If you would like to subscribe the best way is through Substack here:
https://gerarddevalence.substack.com
Thank you
Gerard