A Short History of Building Procurement: Part 3
By the beginning
of the 1800s builders were becoming recognised as an occupation, and as their
firms developed they often specialised in certain types construction, such as
civil engineering during the boom in railway building later in the century. Others,
such as William Cubitt, became developers, building housing to meet demand from
the rapid growth of cities. By the middle of the 19th century large
contracting businesses had taken on the form that in many ways we still see
today, and procurement and contracting was using the same, or a recognizably
similar, system.
There were two
key characteristics of this new procurement system. First was the use of
detailed drawings and design, completed before the work began. The second was
the preparation of cost estimates for the project, on the basis of the design
drawings. The two significant outcomes of these characteristics, that became
the foundations of the modern system, were the shift to competitive tendering
and the growth of the professions.
The construction
of Westminster in the 1830s was one of the first buildings to be done with
detailed drawings from the architect and a bill of quantities (BQ) with full
estimates based on them. Under the system of measure and value costs had been
determined on completion by a measurer, originally a tradesman, and over time this
became a specialised task. As the new method of procurement and contracting
appeared measurers became more important, as prices had to be agreed between
the architect, client and builder before work began. Measurers became quantity
surveyors.
A series of
government commissions on building procurement produced reports that sometimes,
but not always, favoured competitive tendering. Nevertheless, as the system
became more widespread government departments came round to the idea that it
was the best way of obtaining value for money. By the middle of the 19th
century competitive tendering on the basis of design and price specification
had become the usual practice.
The new
profession of quantity surveying was therefore an essential element in the new
system. The procurement method where clients invite tenders on the basis of
completed designs made it necessary for the client to know whether the tender
prices were reasonable, so every element of the design had to be quantified in
terms of materials and labour, and priced. While bills of quantities date back
to the middle of the 18th century, by the close of the century
something close to a modern BQ was coming into use. An 1828 parliamentary
committee investigating the Office of Works and Public Buildings found the
practice had become well-established. So bills of quantities become fundamental
to the contracting system in Britain, and later became part of the required
contractual documentation. It is worth noting that other European countries did
not find the detailed bill as essential.
Not all of the
projects using the new system were won through competitive tendering, often
contracts were negotiated with firms familiar to the client or architect. In
these early days of fixed-price contracting, the idea of competition was
controversial. Much of the opposition to the contracting system was really
opposition to competitive tendering, rather than to the idea of a single
contract with an agreed sum. Competition was believed to lead to lower
standards as contractors would bid low to win work and could not possibly match
those prices without reducing standards.
It was also
feared the contractors would abuse the system through collusion on bid prices
or corrupt practices. Fears that have been justified more than once, as too bid
rigging, cover pricing, unsuccessful tender fees and market sharing, which were
all reported to occur then are sometimes found today. The protection against
such practices was initially based on the idea of only employing ‘respectable’
builders, and the idea of respectability was seen as protection against the
consequences of competition. Rather than reliance on builders’ respectability
the best protection against abuse came to be seen as careful pricing of
specifications and close supervision of the work by the architect, or other
agent.
One key element
of the builder’s respectability was possession of sufficient capital and
employees to carry out a job without subcontracting, which was regarded as a
dubious practice. Clients wished to avoid subcontracting, so it was often done
secretly. The original large contractors employed craftsmen in every trade and were
expected to complete most of a project under their own management. However, the
advantages of subcontracting led to its widespread adoption by the middle of
the 19th century. The advantages then still exist today, such as
flexibility of employment, managing risk and liability, and specialisation,
which was important as the development of new materials and new components
required new skills (for example patent glazing, iron and steel frames, gas,
and later electrical and lighting).
This was also
a time a rapid technological innovation and development, both by and for
contractors. Satoh has six chapters on 19th century technical
advances in his Building in Britain,
covering: stone, wood, bricks, components, pumps and lifting machinery. Like
other industries the widespread availability of steam power was
transformational in the application of new machinery in the contractors’
workshops, and the use of mechanization on building sites slowly increased.
There was also an ongoing transfer of site work into the workshops. For the
largest firms these were huge, William Cubitt (contractor brother of property
developer Thomas Cubitt) had 25 acres on the Isle of Dogs in 1845, complete
with wharves, sawmills, cement kilns, an iron foundry, brickfields, a pottery
and so on, linked by an internal railway and employing about 800 men.
In 1834 the
Builders’ Society was formed in London, partly in response to the rise of the
labour movement as the influence of the guilds declined with competitive
tendering, and by coincidence the same year as the founding of the Royal
Institute of British Architects (RIBA). Its main purpose however, according to
Satoh (1995: 96), was to hold together builders “who being asked to tender on a
specification that did not contain an arbitration clause had all declined. The
arbitration clause seems to have indicated what was to be done in the case of
controversy between owner and builder.” These arbitration clauses were the
source of many disputes and conflicts between contractors and architects, and led
eventually to the Conditions of Contract agreement, much later.
Architects
strongly favoured traditional contracts for price over contracting in gross, at
a fixed sum for the whole project. The reason given by Satoh is “the tedium of
preparing the correct drawings and specifications beforehand” (1995: 292)
rather than preparing designs and giving directions as the work progressed, as
they used to do. However, as conflicts between owners and contractors became
more common, and intense, under the new competitive system, architects realized
the importance of the role of the project superintendent. With the central role
of the architect as client representative becoming established, the RIBA wanted
to ensure architects were seen as acting on behalf of their clients. Concerned
about potential conflict of interests and protecting clients the RIBA, in 1887,
prohibited members from getting involved and profiting from the organisation of
building work.
The idea of
the contract is to make clear what the obligations of each party has, but no
one has ever devised a contract that eliminates all possibility of disputes
over interpretation and performance. As the contracting system developed it was
the architect who came to determine the conditions under which work was let,
and was responsible for resolving disputes. Under the modern system these
contracts gave architects a unilateral power to determine payment to
contractors, which was sometimes abused to benefit clients, and was the source
of bitter complaints from contractors.
In 1870 the
terms of a document called the Heads of Conditions of Builders Contracts was
agreed between architects (RIBA) and the Builders’ Society This established the
basic outline and principles of the standard building contract which could then
be varied to particular circumstances, and addressed the concern of builders
who felt that previous contracts made no provision for variations in materials prices
or the cost of extra work. Bills of quantities were introduced as part of the
contract in 1902, after many revisions in the meantime, and this remained the
basic form until 1931 when the Joint Contract Tribunal was set up and the
standard forms of contract came into use. These are still the basis of the
majority of building contracts in the UK today.
As well as the
conflicts between architects and builders, there was considerable rivalry
between architects and engineers. This began in the early 19th
century as the pace of technological innovation increased and new materials
arrived – iron, then steel, followed by reinforced concrete at the end of the
century - and mechanical engineering emerged (a British specialization) with
the new machines. Architects knew little
about these innovations and left them to engineers. By 1800 architecture and
engineering were separate professions with separate training. Architects
studied with older architects and in schools of architecture, while engineers went
to engineering faculties. The antagonism found in the UK between architects and
engineers in the early 19th century was also present in America.
Fitch (1973: 126) describes a ‘great schism’ that developed as architects
struggled to master the requirements of new forms of building and new materials
and the mutual contempt between them and the new profession of engineers.
The disengagement
of architects and design from building and construction occurred at a time when
engineers were also focusing on design rather than delivery, due to increasing
specialisation and differentiation between different types of engineers (such
as mechanical, structural, civil, electrical and sewerage). Both architects and
engineers neglected estimating, which was left to the new profession of
quantity surveyors. Thus each of the construction professions developed their
own language, skill sets, and cultures, nevertheless sharing a mutual sense of
superiority over builders and contractors.
Moving On
By the end of
the 19th century in the UK there was a fully developed procurement
and contracting system with practices well understood by all the parties
concerned, and this system continued, with its essential characteristics
unchanged, into the 20th century. Nevertheless, it also continued to
generate controversy and conflict, and an increasingly litigious industry.
In the first
half of the 20th century the modern system was refined and further
developed. Bowley (1966) outlined four new ways of contracting as
characteristic of the period between 1944 and 1960s. First was selective
tendering, where only contractors known to be capable are invited to tender.
Second were negotiated contracts, often used by local housing authorities to
bring the contractor in at an earlier stage. Third was serial contracts, with
contractors having successfully completed one project were re-engaged on later
ones. Fourth were package deals as they were called then, now more commonly
referred to as design and build, used particularly for the mass housing
programs with high-rise buildings in the 1960s.
None of these
were really new. All of them had been used before in various forms and they
have all reappeared, sometimes renamed, at various times, to the present. A
proliferation of contract forms continued, as attempts to overcome inadequacies
of the traditional system, into an ever expanding variety of contracts and
procurement systems to choose from. How effective this has been is a topic in
its own right.
On procurement Bowley (1966: 352) said “It is difficult to see how any system more wasteful of technical knowledge, intellectual ability and practical and organising experience could have been invented.” While it is hard to disagree with the sentiment, this rather seems to overlook the evolution of procurement methods as new versions, and contracts, developed as a response to problems and issues found in existing procedures.
On procurement Bowley (1966: 352) said “It is difficult to see how any system more wasteful of technical knowledge, intellectual ability and practical and organising experience could have been invented.” While it is hard to disagree with the sentiment, this rather seems to overlook the evolution of procurement methods as new versions, and contracts, developed as a response to problems and issues found in existing procedures.
Conclusion
This history
of building procurement has focused on England and its development in London, because that
is where many of the major projects were built. These developments are widely
relevant today because England shaped much of modern language, laws, institutions,
and governance. Competitive tendering, enforceable contracts, subcontracting,
surveying and measurement of costs with a BQ are now widespread, but these all came
with the modern system that was developed in the UK. Other countries have
different histories, especially the US and elsewhere in Europe, but the modern
system of procurement and English common law is the foundation on which they
are built.
What this
short history shows is how, over a period of 200 years, a system of procurement
and contracting based on measurement and specification, replaced the older
systems of direct employment of craftsmen at day rates and measure and value.
As this new system was developed and maintained it had great continuity, and is
an important element in understanding how difficult innovation in procurement
actually is. The surprisingly few fundamental changes seen since the modern
system of procurement came into widespread use in the early 19th
century does not mean there have been no changes. What the history shows is
that procurement methods evolve slowly, in response to problems and issues with
the methods in use and to changes in both the organization of work and the
structure of society.
Despite being
constantly criticised and modified around the edges, procurement at the end of
the 20th century is still found have serious issues and be in need
of radical change. Inquiries in many countries (such as the UK, Australia,
Singapore, Hong Kong, Japan, Holland) came to the conclusion that deficiencies
in procurement should be remedied, often by government intervention and/or
contractual reform. In one view:
It is like a game. There are rewards
and penalties, rules and roles. Some cheat, or at least take advantage, where
others wouldn’t. Some play the game straight and true, others are always
looking for an angle to make another dollar or two. Or three. Contracts
describe what is to be provided under what conditions. Some people put the
contract in a desk drawer and forget about it, others use it as a means of
extracting increased payments. The contract sets the rules but it is the
individual who decides how play will be conducted. (Morris 2013: 176).
These comments
echo those made in the mid-nineteenth century. Satoh closes his book with a
series of quotes from opponents of the modern system (1995: 297-99). These
include: poor quality work due to low price bidding, or subcontracting;
builders undercutting each other to win work; the lack of provision for
variations in fixed price contracts; unjustified claims by contractors;
arbitrary decisions by superintendents and architects; non-payment by clients; and
collusion between contractors. To address these issues the contracting system incorporated
increasingly detailed drawings and specifications, and a schedule of prices was
often attached for claims and variations. The unilateral nature of the contract
led to the drafting of the Conditions of Contract, which were revised over
time.
In many ways, in procurement
and contracting in the building and construction industry, the more things
change the more they appear to stay the same. This may, however, not be true of
the 21st century.
This is part 3 of a three part series, the preceding parts are on Pre-Modern Building Procurement and The Great Transition. A pdf of the full document is here.
Awesome thoughts!
ReplyDeleteQuantity Surveyor Cost