Monday 2 May 2016

Sunlight is the Best Disinfectant



Collusion and Corruption in Canadian Construction

By coincidence, around the same time as Dyson Heydon was delivering his Royal Commission’s report to the Australian Government, in Canada another Commission had also found collusion and corrupt behaviour in the construction industry in Quebec. The problems of collusion and corruption are of course not unique to Australia and Quebec, as the Netherlands twelve years ago and Spain in 2014 demonstrate.

The findings from both inquiries on organised crime and a culture of lawlessness in the construction industry are disturbingly similar. Both Commissions identified various causes for the illegal activities they found to be pervasive in construction. How many recommendations get implemented by their respective Governments remains to be seen, although the Commissions’ findings and recommendations provide all the justification needed.

The Report of the Commission of Inquiry on the Awarding and Management of Public Contracts in the Construction Industry, headed by Justice France Charbonneau, was released in November 2015. The Report (4 volumes and 1,741 pages) made 60 recommendations to prevent collusion and corruption in the construction industry, and links with organized crime. Unfortunately, the report is in French so this post is drawn from English language coverage, not the original documents (including here for the recommendations, here for the main witnesses and their testimony, and here for context).

Following a 2009 Radio-Canada broadcast into corruption inside Quebec’s biggest construction union, a joint investigation was carried out by Canada’s Competition Bureau and Unité Permanente Anticorruption, an anti-corruption unit established by the Government of Quebec. The investigation uncovered evidence of a scheme giving preferential treatment to a group of contractors in municipal contracts, mainly for infrastructure projects.

As a result of that investigation, 77 criminal charges were laid against nine companies and 11 individuals in 2012. These charges included 20 counts of bid-rigging under the Act against nine companies and 24 counts of bid-rigging against six individuals. Other criminal charges included corruption in municipal affairs, breach of trust, improperly influencing municipal officials, fraud, production and use of counterfeit documents, secret commissions, misrepresentations or false statements, extortion and conspiracy.

The Charbonneau Commission was set up by the Government of Quebec in 2011 to look at cases of collusion and corruption in Montreal over 15 years between 1996 and 2011. The terms of reference included financing of political parties and organized crime in the construction industry, and recommendations for remedial measures to identify, eliminate and prevent collusion and corruption. Another 37 people, including two mayors, were arrested in 2012.

The commission shone a light on politicians’ and public officials’ relationship with construction and related service companies over more than two decades. It concluded that a link existed between political party financing and public contracts, calling the practice deep rooted and systemic. Several recommendations focused on reforms to political financing rules. Quebec’s strict laws governing political donations mean parties are unable to raise enough money for campaigns from individuals but are prohibited from receiving corporate donations. What happens instead is corporate donations funneled through proxies. This is illegal.

The scale of the system, however, extended much further. It linked construction firms, many with mafia ties, and a cabal of consulting engineers to politicians and managers in Montreal. Corrupt practices included kickbacks, illegal campaign contributions, rigged contracts with mafia payoffs, limiting competition for projects to a favoured few with the right political and/or mafia connections, and using threats to discourage competition by persuading potential bidders to withdraw. The Commission differentiated this kind of tacit collusion, where reputable firms withdraw from the market, from political corruption, where companies illegally contribute to political parties or candidates.

The Commission investigated the consulting engineering industry in Quebec and made a number of significant recommendations. Quebec is the only jurisdiction in Canada that does not allow a professional order to impose disciplinary sanctions on a partnership or a corporation that provides professional engineering services. This limits its supervisory powers to engineers as individuals.

Corrupt public authorities imposed unreasonably short deadlines for tenders, to benefit one bidder. Substantial and late alterations to a project, often described in addenda, without adjusting the tender filing deadlines, had the same effect. The case of Montreal's procurement of water meters was cited as an example of this.

Commissioner Charbonneau concluded corruption and collusion are "far more widespread than originally believed" and found that organized crime had indeed infiltrated the industry. The Italian Mafia was deeply involved in the industry and significant sections of the report were blacked out because of criminal cases before the courts.

Commissioner Charbonneau found several causes, connected with the public procurement of construction projects, for the various schemes uncovered during the inquiry. Major failings in procurement strategies, in particular the lack of expertise, resulted in public bodies being exposed to a high risk of collusive agreements. For example, the non-negotiable tariff contracts, called “rate-setting contracts”, set a price for manufacturing and laying asphalt a geographical area. The effect is that the contracts allow the asphalt plants owners to divide up territories.

There were also transparency issues. Examples were the release on request of the list of contractors who have the specifications or tendering documents, and the release of cost estimates for projects. The Commission noted that it was well-known the bid bonds Montréal requires for tenders are 10% of the estimated cost of the project. By disclosing the amount of the bond security required, the City was publishing the amount that it expected to pay.

A small group of union halls were allowed to dictate who is hired for each job, although around 70 percent of Canadian construction workers are not unionized. The testimony at Charbonneau was often salacious, with tales of the Province's largest union being infiltrated by the Mafia and Hells Angels, death threats for dissenters, million dollar investments of union funds in biker-owned strip clubs and massive financial fraud involving some labour leaders.

The Commission was asked to make recommendations, and the first recommendation was a Procurement Authority, a centre of expertise for procurement processes to support and oversee public bodies. In the words of the Commission: “The lack of personnel and the loss of expertise may have created fertile soil for collusion.” The Commission also recommended the various public authorities consolidate their internal expertise in construction.

The second recommendation was to vary the rule requiring contracts to be awarded to the lowest conforming bidder, arguing the strict rule of winning public contracts as lowest tenderer facilitated collusive agreements, based on the cartel's ability to control the results of calls for tenders.  Also the mandated 15 day tender period should allow adjustment for project complexity.

The Commission recognized long payment delays restrict competition in the industry, a factor in the creation and continuation of collusive agreements. Contractors bear the cost of payment delays and the lack of funds limits the numbers and growth of contractors. In 2013, more than three-quarters of contractors were said to have not responded to at least one call for tenders, because they viewed the payment clauses as abusive or they anticipated payment problems.

The other recommendations covered whistleblower protection, financial transparency, and relationships between officials, politicians, unions and contractors. There was some criticism that the recommendations were too moderate and lacked bite.

In its details the operation of this system was unique to Quebec and Montreal, due to cultural and institutional factors. However, the incentives inherent in the transactions between construction contractors and governments inevitably provide opportunities for side deals, collusion and corruption. And in Quebec these had become entrenched. Despite critics claims the Charbonneau Commission was too expensive and ineffective it did what any good anti-corruption inquiry should do, shine a light on the institutions and people involved. Sunlight is the best disinfectant.



Wednesday 13 April 2016

Procurement case study: Holyrood 1997



 The Holyrood Building
 
The story of the building of the new Scottish parliament house, The Holyrood Building, is another instructive case study. In 1997 it was announced that the new parliament building was to be constructed and the cost estimate was £40 million. A design competition was held, one year later in 1998, and a construction management contract was awarded to Bovis Lend Lease at the beginning of 1999. 

The initial client was the Scottish Office, then after work started this was transferred to the Parliamentary Corporate Body, and later the Presiding Officer and an architectural advisor were added. A report in 2000 identified poor communication between the client and contractors as increasingly costly.

Contracts were based on concepts, not on a detailed finished design. The concept design also changed during construction, with floor space first increasing from 11,000 m² to 18,000 m² and ending up at 33,000 m². There were also increased anti-terror security measures including toughened glazing, which added another 10% to the final cost.

This all led to very many variations, in a six-month period between October 2002 and May 2003 there were 1,825 architect instructions which led to 4,600 instructions to trade contractors, with nearly 5000 variations in six months. Despite a design freeze that began in April, in May 2003 there were another 545 architect’s instructions. The time and cost implications are obvious. A report by the Auditor General in 2004 concluded that over 2000 design changes to the project were a major factor in the cost overrun.

During construction the lead architect died and the project director resigned. There were conflicts between the two architectural practices involved, and between them and the contractors. The Fraser Inquiry was critical of their dysfunctional relationship, poor communication and their claim, “without basis” that the building could be completed for £50 million.

By June 2001 the costs had escalated to £230 million. In 2002 the cladding contractor went into liquidation and the price increased to £300 million. By the time the building opened in September 2004 it was three years late and had cost a great deal more than the initial estimates. The eventual cost reported in 2007 was £414 million, 10 times the original estimate.

An inquiry was set up and the report was published in 2004. A major focus of the Fraser Inquiry was whether the procurement method or the client had caused the problems. A construction management contract is typically used on integrated design and construction projects, which is its strength, but is not particularly good at managing budgets. The original budget was obviously much too low, and this led to a lot of unwanted and probably unnecessary publicity about cost overruns. The main findings of the inquiry were the unrealistic nature of the initial cost estimates, use of a procurement model that passed risk wholly onto the state client, conduct of the tendering process and choosing the contractor, and security concerns that added to the cost but could have been anticipated. The conduct of civil servants was questioned.

The Fraser Inquiry identified two fundamentally flawed decisions. The first was procurement using a construction management contract instead of a Private Finance Initiative contract. Second was the insistence on a rigid program. The Scottish Office decided to use a construction management contract to speed construction, but without evaluating the financial risks of doing so, and without asking Ministers to approve it. Officials decided that rapid delivery of the new building was to be the priority, but that quality should be maintained, so cost blowouts were inevitable.

The client was obsessed with early completion and failed to understand the impact on cost and the completion date if high-quality work and a complex building were required. In attempting to achieve early completion, the management contractor produced optimistic programs, to which the architects were unwise to commit. The main causes of the slippage were delays in designing a challenging project that was to be delivered against a tight timetable.

Perhaps most damning in the inquiry’s report was the finding that senior civil servants withheld information on the problems between contractors and architects and the rising cost of the project from ministers. Ministers were not informed of concerns within the Scottish Office over the cost of the project and officials did not take the advice of the cost consultants, a serious failure of accountability.

In the final indignity the completed project suffered from flooding, as the original site had been a brewery and there were hidden underground springs. Then in 2006 one of the beams in the debating chamber swung loose due to missing and damaged bolts and poor glue, and the MPs were evacuated.

The lesson that is usually drawn from the Scottish Parliament building is that the client did not know what they wanted and proceeded with a brief that was poorly developed. However, the conduct of the civil servants involved was, in my view, deplorable. After the Fraser Inquiry’s report was handed down there were further investigations by the Scottish Parliament into their conduct, however no action was taken against any of the individuals involved.

Clearly, when civil servants get involved in these large complex projects, guidelines on governance need to be established and rigorous standards need to be enforced. One of the recommendations of the report was that independent advisers should be employed and those advisers need to have direct access to ministers, without their advice being filtered by public officials.

Holyrood is an extensively documented project. The link to the Fraser Inquiry report is below, the Conclusions and Findings are the most relevant. There is a Wikipedia page that is comprehensive, including a timeline of cost increases and many links.



This is one in a series of procurement case studies. Other ones are on the building of the British parliament house at Westminister in 1837 and Heathrow Terminal 5